Talimarjan Power Project (formerly CASAREM–Talimarjan Energy Development Project)

Summary

The project includes

  • detailed design, construction, installation, and commissioning of two combined cycle gas turbine units with installed capacity of approximately 370 megawatts (MW) - 450 MW each, and related infrastructure at the Talimarjan thermal power plant;
  • building of a community service center for power plant employees and families; and
  • a special capacity development component to support the improvement of Uzbekenergo's management, financial, and operational performance.

Expected Outcome

The project will improve energy security in Uzbekistan and facilitate regional energy trade.

Expected Outputs

  • Two combined cycle gas turbine units in Talimarjan thermal power plant commissioned.
  • Community service center operational.
  • Uzbekenergo corporate management and performance improved.

Project Types

Loan

Funding

Funding AgencyAmount (USD millions)Notes
Asian Development Bank 350
Japan International Cooperation Agency 300
Fund for Reconstruction and Development of the Republic of Uzbekistan 250
Uzbekenergo 150
Government of Uzbekistan 230
Total 1,280
...