Power Sector Rehabilitation Project (formerly Power Transmission Rehabilitation)

Summary

The project will help rehabilitate the 1,200-megawatt Toktogul hydroelectric power plant, which is critical to national and regional power supply.  The project will also establish an electricity transactions settlement center to reduce commercial losses, conduct safety assessment of dams on the Naryn cascade, and launch a public information program on power sector reforms.

Expected Outcome

The project will improve the performance of the Toktogul hydroelectric power plant and increase the reliability of national and regional power systems.

Expected Outputs

  • 1,200 MW Toktogul HEPP rehabilitated.
  • Electricity transactions settlement center established.
  • Dam safety assessed.
  • Public information program delivered.

Project Types

Grant, Loan

Funding

Funding AgencyAmount (USD millions)Notes
Asian Development Bank 40 Grant
Asian Development Bank 15 Loan
Government of the Kyrgyz Republic 7
Total 62
...