CASAREM-Talimarjan Power Generation and Transmission Project

Summary

The original aim of the technical assistance (TA) was to prepare the Talimarjan Power Project for Asian Development Bank financing. The TA scope was expanded to include assistance to the EA in procuring the main power plant contract.    

Expected Outcome

The project will increase the generation capacity and strengthen the transmission network in Uzbekistan.

Expected Outputs

  • Analysis of electric sector including justification of project need
  • Assessment of appropriateness of project technical design
  • Project financial and economic analysis and financial assessment of Uzbekenergo
  • Environmental Impact Assessment
  • Social safeguard assessment to include LARP, Poverty and Social analysis, and IPDP (if required)
  • Bid specifications for project implementation
  • Tender evaluation

Project Types

Technical Assistance

Funding

Funding AgencyAmount (USD millions)Notes
Asian Development Bank 1.5
Government of Uzbekistan 0.375
Asian Development Bank 0.6 Supplementary, approved 2011
Total 2.475
...